The project also includes new guard railing, and the addition of numerous safety features.
Preliminary work will begin on May 23, with nightly one-way traffic control. SR 99 will be fully closed to through traffic tentatively on June 6th for seven weeks. Please see the attached detour map to plan your commute/trips accordingly.
The $7.5 million project includes 90 working days, with 40 calendar days requiring the SR-99 closure. The entire project is expected to be completed by mid-August 2022.
To stay up to date on highway projects, please follow us on Facebook and Twitter. Project information can also be found on the District 2 webpage.
The public can also call 530-225-3426 during working hours or send an email to
Updated highway conditions for California can be found on QuickMap and on One-Stop-Shop for the Western U.S.
Contractor Viking Construction Co. Inc., North Region Construction and Caltrans District 2 thank the traveling public and local communities for their patience during the construction of the project.