NORTH‌‌ ‌‌COAST, ‌‌ ‌‌Calif. — Caltrans‌‌ ‌‌reports‌‌ ‌‌that‌‌ ‌‌the‌‌ ‌‌following‌‌ ‌‌road‌‌ ‌‌projects‌‌ ‌‌will‌‌ ‌‌be‌‌ ‌‌taking‌‌ ‌‌place‌‌ ‌‌‌around‌‌ ‌‌the‌‌ ‌‌North‌‌ ‌‌Coast‌‌ ‌‌during‌‌ ‌‌the‌‌ ‌‌coming‌‌ ‌‌week. ‌‌ ‌‌‌ ‌
‌‌‌ ‌
Included‌‌ ‌‌are‌‌ ‌‌Mendocino‌‌ ‌‌County‌‌ ‌‌projects‌‌ ‌‌that‌‌ ‌‌may‌‌ ‌‌impact‌‌ ‌‌Lake‌‌ ‌‌County‌‌ ‌‌commuters, as well as work in Del Norte and Humboldt counties.
‌‌‌ ‌
Caltrans‌‌ ‌‌advises‌‌ ‌‌motorists‌‌ ‌‌to‌‌ ‌‌drive‌‌ ‌‌with‌‌ ‌‌caution‌‌ ‌‌when‌‌ ‌‌approaching‌‌ ‌‌work‌‌ ‌‌areas‌‌ ‌‌and‌‌ ‌‌to‌‌ ‌‌be‌‌ ‌‌prepared‌‌ ‌‌to‌‌ ‌‌stop‌‌ ‌‌at‌‌ ‌‌traffic‌‌ ‌‌control‌‌ ‌‌stations. ‌‌ ‌‌‌ ‌
‌‌‌ ‌
The‌‌ ‌‌Caltrans‌‌ ‌‌Traffic‌‌ ‌‌Operations‌‌ ‌‌Office‌‌ ‌‌has‌‌ ‌‌reviewed‌‌ ‌‌each‌‌ ‌‌project‌‌ ‌‌and‌‌ ‌‌determined‌‌ ‌‌that‌‌ ‌‌individual‌‌ ‌‌‌project‌‌ ‌‌delays‌‌ ‌‌are‌‌ ‌‌expected‌‌ ‌‌to‌‌ ‌‌be‌‌ ‌‌less‌‌ ‌‌than‌‌ ‌‌the‌‌ ‌‌statewide‌‌ ‌‌policy‌‌ ‌‌maximum‌‌ ‌‌of‌‌ ‌‌30‌‌ ‌‌minutes‌‌ ‌‌unless‌‌ ‌‌‌noted‌‌ ‌‌otherwise. ‌‌ ‌‌‌ ‌‌‌ ‌

For‌‌ ‌‌updates‌‌ ‌‌to‌‌ ‌‌this‌‌ ‌‌list‌‌ ‌‌check‌‌ ‌‌QuickMap‌‌ ‌‌at‌‌ ‌‌‌www.dot.ca.gov‌‌‌ or‌‌ ‌‌1-800-GAS-ROAD‌‌ ‌‌‌(1-800-427-7623). ‌‌ ‌‌‌ ‌

LAKE COUNTY

Highway 20

— Road work west of Upper Lake at Blue Lakes Road will occur on Monday, July 17, and Tuesday, July 18. One-way traffic control will be in effect from 8 a.m. to 4 p.m. Motorists should expect up to five-minute delays. LC#F20AA

— Utility work in Clearlake Oaks will occur at Private Road on Monday, July 17. One-way traffic control will be in effect from 8 a.m. to 4 p.m. Motorists should expect up to five-minute delays. LC#P20BA

— Utility work will occur at Abbot Mine Road on Tuesday, July 18. One-way traffic control will be in effect from 8 a.m. to 4 p.m. Motorists should expect up to five-minute delays. LC#P20BA

Highway 29

— Utility work in Middletown from Wardlaw Street to Saint Helena Creek will occur on Monday, July 17. One-way traffic control will be in effect from 8 a.m. to 4 p.m. Motorists should expect up to five-minute delays. LC#P29DA

— Utility work will occur in Lower Lake from south of Clayton Creek Road to Route 53 on Wednesday, July 19. One-way traffic control will be in effect from 8:30 a.m. to 4 p.m. Motorists should expect up to five-minute delays. LC#P29DA

— Road work east of Kelseyville will continue from Route 281 to Private Drive. Lane closures will be in effect and motorists should anticipate up to 15-minute delays. LC#C29FA

Highway 175

— Tree work west of Diener Road continues. One-way traffic control will be in effect from 7 a.m. to 6:30 p.m. Motorists should anticipate up to 10-minute delays. LC#C175KA

— Bridge work in Cobb at Bottle Rock Road will continue. One-way traffic control will be in effect from 7 a.m. to 5 p.m. Motorists should expect up to five-minute delays. LC#C175RA

— Road work near Putah Creek west of Socrates Mines Road began Friday, July 14. One-way traffic control will be in effect from 7 a.m. to 6:30 p.m. Motorists should anticipate up to 10-minute delays. LC#C175JA

MENDOCINO COUNTY

Highway 1

— Bridge work in Fort Bragg from Manzanita Street to Pudding Creek Road continues. One-way traffic control will be in effect and motorists from 9 a.m. to 7 p.m. can expect up to 20-minute delays Monday through Friday and 30-minute delays are anticipated on the weekends. A full nighttime road closure at the Pudding Creek Bridge will occur on Tuesday, July 18, and Wednesday, July 19 from 10 p.m. to 4 a.m. LC#C1OB

Highway 20

— Paving work near Road 10 will continue. One-way traffic control will be in effect from 7 a.m. to 6 p.m. Motorists should expect up to 10-minute delays. LC#C20IB

— Tree work west of Three Chop Road continues. One-way traffic control will be in effect from 7 a.m. to 4 p.m. Motorists should expect up to five-minute delays. LC#C20BA

Highway 101

— Road work from Comminsky Station Road to the Pieta Creek Bridge began on Friday, June 23. Lane closures will be in effect from 6:30 a.m. to 5 p.m. and motorists should expect minor slowdowns. LC#C101KC

— Paving work south of Willits from Route 20 to Uva Drive in Redwood Valley will begin on Monday, July 17. Lane closures will be in effect from 6 a.m. to 6 p.m. and motorists should expect minor slowdowns. LC#M101Q

— Emergency work in Willits from Water Plant Road to the East Hill Undercrossing continues. Lane closures will be in effect and motorists should expect minor slowdowns in the area. LC#C101ND

— Culvert work in Piercy north of Exit 627 continues. Lane closures will be in effect from 4:30 p.m. to 6 p.m. Motorists should expect up to 10-minute delays. LC#C101ED

— Bridge work from the Lowell Allen Memorial Bridge to Route 271 continues. Lane closures will be in effect and motorists can expect minor slowdowns in the area. LC#C101JD

— Emergency work between Piercy and Benbow near Milkyway Loop Road continues. One-way traffic control is in effect and motorists should expect up to five-minute delays. LC#T101IA

Highway 162

— Utility work north of Road 8158 will occur on Friday, July 14. One-way traffic control will be in effect from 8 a.m. to 4 p.m. Motorists can expect up to five-minute delays. LC#P162BA

— Road work south of Dos Rios near the Rodeo Creek Bridge continues. One-way traffic control will be in effect from 3 p.m. to 7 a.m. weeknights. Motorists should expect up to 10-minute delays. LC#C162GA

Highway 253

— Utility work at Singley Cattlepass began on Friday, July 14. One-way traffic control will be in effect from 7 a.m. to 5 p.m. Motorists should anticipate up to 15-minute delays. LC#C253DA

Highway 271

— Culvert work in Piercy from south of Bear Pen Road to north of County Road 442B continues. A full lane closure is in effect from 7:00 a.m. to 6:30 p.m. and motorists should expect up to five-minute delays. LC#C271EA

— Road work in Piercy continues. A full lane closure is in effect from 7 a.m. to 6 p.m. Motorists should use an alternative route. LC#C271IA

DEL NORTE COUNTY

Highway 101

— Bridge work between Peine Road and Old Hunter Creek Road will continue. One-way traffic control will be in effect. Motorists should anticipate up to 10-minute delays. LC#C101KB

— Construction in the Last Chance Grade area will continue. Additional emergency storm cleanup work is also in progress. One-way traffic control will be in effect. Motorists should anticipate a total of up to 30-minute delays. LC#C101ID, and C101OC

— Emergency work south of Crescent City from Enderts Beach Road to Humboldt Road will continue. Southbound lane closures will be in effect and motorists should anticipate minor traffic slowdowns. LC#M101AA

HUMBOLDT COUNTY

Highway 36

— Bridge work from Pamplin Grove to Redwood House Road will continue. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays. LC#C36UA

— Slipout repair near Burr Valley Road will continue. One-way traffic control will be in effect. Motorists should anticipate five-minute delays. LC#C36DA

Highway 96

— Construction work near Bluff Creek Road will continue. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays. LC#C96LA

— Bridge work at Aiken Creek Bridge and Bluff Creek Bridge will continue. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays. LC#C96KA

Highway 101

— Drainage work north of Dean Creek Bridge will begin on Sunday, July 16. Lane closures will be in effect. Motorists should anticipate minor traffic slowdowns. LC#C101OD

— Drainage work from Salmon Creek Road Overcrossing to Eagle Point Viaduct will begin on Sunday, July 16. Lane closures will be in effect. Motorists should anticipate minor traffic slowdowns. LC#C101OD

— Bridge work at Myers Flat Bridge continues. Lane closures will be in effect from 7 a.m. to 7 p.m. In addition, full on and off ramp closures will be in effect. Motorists should anticipate minor traffic slowdowns. LC#C101ZC

— Various improvements between Grant Street and 5th Street will continue. Lane closures will be in effect from 8 p.m. to 7 a.m. Motorists should expect minor traffic slowdowns. LC#P101HA and C101HD

— Construction work from Cole Avenue to Jacobs Avenue will conclude on Monday, July 17. Lane closures will be in effect from 8 p.m. to 6 a.m. Motorists should anticipate minor traffic slowdowns. LC#C101FD

— Striping in the Big Lagoon area will continue. Lane closures will be in effect from 7 a.m. to 7 p.m. weekdays. Motorists should expect minor traffic slowdowns. LC#C101ZC

— Roadway excavation in Orick will begin on Monday, July 17. One-way traffic control will be in effect from 7 a.m. to 5 p.m. weekdays. Motorists should expect up to 10-minute delays. LC#C101SD

Highway 169

— Bridge work at Rube Creek Bridge will continue. One-way traffic control will be in effect. Motorists should anticipate minor traffic slowdowns. LC#C169AA

— Drainage and paving work north of Weitchpec will conclude on Tuesday, July 18. One-way traffic control will be in effect from 7 a.m. to 3:30 p.m. Motorists should anticipate 10-minute delays. LC#C169BA

Highway 254

— Construction work along Avenue of the Giants will continue. One-way traffic control will be in effect from 7 a.m. to 7 p.m. Motorists should anticipate 10-minute delays. LC#C254IA

— Bridge work between State Park Road and Fish Creek Road will continue. A full closure of this portion of highway will be in effect and motorists should choose an alternate route. LC#C254CA

— Road work north of Fish Creek Road continues. One-way traffic control will be in effect. Motorists should expect up to five-minute delays. LC#C254DA

Highway 299

— Falsework installation at Route 200 will continue. One-way traffic control will be in effect. Motorists should anticipate minor traffic slowdowns. LC#C299CA

— Drainage work from Route 200 to Blue Lake Undercrossing will continue. Lane closures will be in effect from 6 a.m. to 8 p.m. Motorists should anticipate minor traffic delays. LC#C299QA

— Full on and off ramp closures at Blue Lake Undercrossing will be in effect from 6 a.m. to 8 p.m. Motorists should choose an alternate route. LC#C299QA

— Drainage work from North Fork Mad River to Simpson Road will continue. One-way traffic control will be in effect from 6 a.m. to 8 p.m. Motorists should anticipate five-minute delays. LC#C299QA

— Construction work near East Fork Campground will continue. One-way traffic control will be in effect. Motorists should anticipate five-minute delays. LC#C299LA

Upcoming Calendar

21Sep
09.21.2024 4:00 pm - 10:00 pm
Passion Play fundraiser
21Sep
09.21.2024 4:30 pm - 10:00 pm
Lake County Wine Auction
23Sep
09.23.2024 6:00 pm - 8:00 pm
Lakeport City Council candidates' forum
24Sep
09.24.2024 10:00 am - 1:00 pm
Farmers' Market at Library Park
28Sep
09.28.2024 10:00 am - 1:00 pm
Farmers' Market at the Mercantile
5Oct
10.05.2024 7:00 am - 11:00 am
Sponsoring Survivorship
5Oct
10.05.2024 10:00 am - 1:00 pm
Farmers' Market at the Mercantile
12Oct
10.12.2024 10:00 am - 1:00 pm
Farmers' Market at the Mercantile
14Oct
10.14.2024
Columbus Day
14Oct

Mini Calendar

loader

LCNews

Award winning journalism on the shores of Clear Lake. 

 

Newsletter

Enter your email here to make sure you get the daily headlines.

You'll receive one daily headline email and breaking news alerts.
No spam.