LAKEPORT, Calif. – Two of the city of Lakeport’s main arterial streets will be getting some improvements in the coming weeks.
The city reported that a chip seal project will take place on 11th Street between Highway 29 and Main Street and on South Main from Peckham Court to Lakeport Boulevard.
The contractor VSS International of West Sacramento will conduct the chip seal work from 8:30 a.m. to 5:30 p.m. Tuesday, July 24. The city said there will be no road closures but traffic control will be in place.
Chip sealing is a rubberized asphalt applied to the existing road surface, which is then covered with aggregate rock, or “chip.” Chip sealing takes a few hours to completely cure.
No parking signs have already been placed along 11th Street in anticipation of the work.
On Monday, July 30, crews will return to put down the micro seal. The city said that work will be completed at night and will require a road closure.