Caltrans plans major roadwork through Dec. 17

Print
NORTH COAST – Caltrans reports that the following road projects will be taking place around Lake County during the coming week.


Included are Mendocino County projects that may impact Lake County commuters.


LAKE COUNTY


Highway 20


– Caltrans will perform routine maintenance from Abbot Mine Road to the Colusa/Lake County line. Work hours are 8:30 a.m. to 3 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays.


MENDOCINO COUNTY


Highway 1


– Pavement repair 0.2 mile north of Big Gulch Road will continue. Work hours are 7 a.m. to 5 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate five-minute delays.

Contractor – Rege Construction Inc. of Cloverdale.


– Construction of a retaining wall about three miles north of Elk will continue. One-way traffic control with a temporary signal will be in effect 24 hours per day, seven days per week. Motorists should

anticipate 10-minute delays. Contractor – Granite Construction of Ukiah.


– The City of Fort Bragg has been granted a Caltrans Encroachment Permit to hold the Holiday Lights Parade between Madrone Avenue and Fir Avenue on Saturday, Dec. 12. Event hours are 6 p.m. to 9 p.m. A full road closure will be in effect. A detour will be available.


– PG&E of Eureka has been granted a Caltrans Encroachment Permit for utility maintenance about 0.7 mile south of Westport on Tuesday, Dec. 15. Work hours are 8 a.m. to 2 p.m. One-way traffic control will be in effect. Motorists should anticipate five5-minute delays.


Highway 20


– Comcast of Ukiah has been granted a Caltrans Encroachment Permit for utility maintenance about 0.3 mile east of Summer Lane on Wednesday, Dec. 16. Work hours are 9 a.m. to 3 p.m. Intermittent full road closures will be in effect. Motorists should anticipate five-minute delays.


– Construction of a retaining wall 0.4 mile east of Three Chop Road will continue. One-way traffic control with a temporary signal will be in effect 24 hours per day, seven days per week. Motorists should anticipate 5-minute delays. Contractor – Granite Construction of Ukiah.


Highway 101


– Bridge deck repairs at the Cummings Road Bridge will continue. Work hours are 7 a.m. to 7 p.m., weekdays. Traffic will be restricted to one lane in each direction of travel. Motorists may experience minor traffic slowdowns. Contractor – DeBruin Construction Inc. of French Camp.


Highway 128


– AT&T of Walnut Creek has been granted a Caltrans Encroachment Permit for utility relocation from 1.5 to 3.5 miles east of Mountain House Road. Work hours are 8 a.m. to 4 p.m., weekdays. One-way traffic control will be in effect. Motorists should anticipate five-minute delays.


For information pertaining to emergency roadwork or for updates to scheduled roadwork, please contact the California Highway Information Network (CHIN) at 1-800-GAS-ROAD (1-800-427-7623).